- Home
- Government
- Town Government
- Departments & Divisions
- Public Works
- Coastal Protection
Current Coastal Protection Projects
Last Content Update:
Mid-Town Beach Renourishment Project
The Mid-Town Beach Renourishment Project will restore sand lost due to storm damage along the federally authorized Mid-Town Beach project area, from Seminole Avenue to Banyan Road. Approximately 480,000 cubic yards of sand will be placed on the beach.
The project is being implemented by the U.S. Army Corps of Engineers (USACE), with the Town of Palm Beach serving as the local sponsor. The Town is grateful for its continued partnership with USACE to protect our shoreline and coastal infrastructure.
Construction Schedule
- Mobilization activities are scheduled to begin on February 17th. Temporary delays are expected at the intersection of North County Road and Sunset Avenue for the delivery of equipment periodically until the end of February.
- Construction is expected to be completed by the end of April.
What to Expect
- Sand will be pumped to the beach via pipeline, then graded and shaped.
- Work areas will be marked with temporary construction fencing and will move along the beach as work progresses.
- Some beach access points may be temporarily closed near active construction areas. Every effort will be made to keep beach access available whenever possible.
- Work will take place 24 hours a day, 7 days a week in order to complete the project in the timeliest manner. Construction must take place during season to avoid work during sea turtle nesting season.
- Construction equipment and materials will be staged primarily at Peruvian Avenue and Sunset Avenue beach accesses. Clarke Avenue beach access will also be used as a staging area.
- Traffic and pedestrian safety measures will be in place around construction areas.
Project Updates
March 18, 2026: Work on the Palm Beach Mid-Town Beach Renourishment Project is progressing. Dredging began on March 6 in the Palm Beach Harbor entrance channel. Since then, more than 56,000 cubic yards of material have been dredged. Sand from the harbor and from a borrow area north of the inlet is being pumped onto the beach and placed along the shoreline between Sunrise Avenue and Breakers Row. Activities have temporarily been paused due to weather and will resume when it is safe to do so.
Sunset Avenue beach access remains closed, and Clarke Avenue beach access may be intermittently closed as work continues nearby. No additional closures are expected in the coming week.
Environmental monitoring is ongoing throughout the project. No incidents involving protected species have been reported, and a leatherback sea turtle nest was successfully relocated from the project area. Water quality is being monitored regularly, and turbidity levels remain within acceptable limits.
Work will continue in the weeks ahead as crews move along the shoreline rebuilding the beach.
As a reminder, please keep a safe distance from equipment, pipes, and active construction areas, and be respectful of construction crews. For your safety, follow all posted signage and avoid entering work zones. Thank you for your continued patience and cooperation as this project progresses.
March 11, 2026: Work on the Palm Beach Mid-Town Beach Renourishment Project is underway.
Dredging began on March 6 in the Palm Beach Harbor entrance channel. Sand from the harbor is being pumped onto the beach and placed along the shoreline between Seabreeze Avenue and Barton Avenue, where crews are actively building up the beach.
Clarke Beach is temporarily closed while sand is being placed in the immediate vicinity, and the Sunset Avenue Beach access remains closed.
Environmental monitoring is ongoing throughout the project. Daily marine turtle surveys began March 1, and no sea turtle crawls have been observed within the project area. Water quality is also being monitored regularly, and results remain within normal levels.
Work will continue over the coming weeks as crews move along the shoreline restoring the beach.
As a reminder, please stay clear of equipment, pipes, and active construction areas and be courteous of construction workers. For everyone’s safety, please follow posted signage and avoid walking through work zones. We appreciate everyone’s patience and cooperation as this important work moves forward!
March 6, 2026: Mobilization is moving along. The dredge arrived this morning, and dredging expected to begin later this afternoon, weather permitting. Sand placement will begin alongside dredging, with sand pumped onto the shore and carefully spread to rebuild the beach, starting near Seabreeze Avenue. Environmental monitoring, including daily sea turtle surveys, is underway.
The Sunset Avenue beach access is closed until the project progresses south. Equipment is currently staged on the beach south of Sunset Avenue and at Clarke Beach. Clarke Beach is currently open but may be temporarily closed when sand is being placed in the immediate vicinity.
As a reminder, please stay clear of equipment, pipes, and active construction areas, and be courteous of construction workers. We appreciate everyone’s patience and cooperation.
February 25, 2026: Mobilization is progressing, and activity will continue to ramp up over the coming weeks.
The Sunset Avenue beach access remains closed while equipment deliveries continue and the project commences. Temporary intersection closures at North County Road and Sunset Avenue are taking place Monday through Friday between 9 a.m. and 3 p.m., with traffic control onsite to keep everything moving safely and efficiently.
The pipeline that will be initially used to pump material onto the beach is currently installed in the vicinity of Seabreeze Avenue.
Dredging is scheduled to begin March 5, with initial sand placement activities starting near Clarke Beach.
Delivery of equipment and assembly of pipeline is also taking place within the Port of Palm Beach Staging Area for this project and for Palm Beach County's Ocean Ridge Beach Renourishment Project. Crews will be assembling pipelines for the Ocean Ridge within the staging area over the next couple of days.
Please stay clear of equipment, pipes, and active construction areas, and please be courteous of construction workers. We appreciate everyone’s patience and cooperation as this important beach renourishment project moves forward.
February 18, 2026: Mobilization is underway! Crews are delivering equipment and preparing both offshore and beach staging areas ahead of sand placement. The Sunset Avenue beach access is closed until further notice as crews are delivering equipment and will be using this area as their primary access for the first part of the project. Temporary intersection closures are expected at North County Road and Sunset Avenue, between 9:00 am and 3:00 pm. The north side of Sunset Avenue will remain open for residential parking. Please observe posted signage and stay clear of marked work zones for everyone’s safety.
Survey and environmental monitoring activities are in progress. Dredging is expected to begin in early March, pending the arrival of the dredge vessel. Once work begins, sand will be pumped onto the beach and graded to restore the shoreline.
This federally funded project is led by the USACE, with the Town of Palm Beach serving as the local sponsor.
Updates will be posted regularly as the project progresses.
Reach 8 and 9 Dune Restoration
The Town of Palm Beach successfully implemented its dune restoration project in Reaches 8 (the Bellaria to La Bonne Vie) and 9 (the Town of South Palm Beach) in November and December of 2025. Beach dunes are a crucial first line of defense against storms and waves. Sand was placed for shoreline protection in accordance with the Town's Beach Management Agreement and Coastal Management Plan.
Between December 9, 2024, and January 24, 2025, approximately 750,000 cubic yards of sand were dredged from an established offshore borrow area and sand piped onto the beach between Phipps Ocean Park and the Ambassador Condominium. Approximately 20,000 cubic yards of sand was then trucked north along the beach and placed as dunes between Phipps Ocean Park and Sloan's Curve. Due to challenges finding access onto the beach south of Lake Worth Pier, the dune restoration project was postponed and completed later in the year outside of sea turtle nesting season.
Dunes were constructed from south of Lake Worth Beach Pier to north of Lantana Beach Park. Sand was sourced from a stockpile between Phipps Ocean Park and the Palm Beach Par 3 Golf Course. Sand was trucked along South Ocean Boulevard/A1A from Phipps Ocean Park to the Atriums Condominium. Conveyor belts were used to carry sand west to east at the Atriums over the existing dune to place sand directly on the beach. Trucks on the beach graded the sand to the project template. Beach access for residents was provided throughout the project, with some areas temporarily closed due to active construction zones. Construction began in November and was completed by December 23rd.
Project Updates
December 22, 2025: Work is wrapping up on the Reach 8 and 9 Dune Restoration Project, with crews completing the final stages of construction.
Sand placement in Reach 8 is complete, and final grading is underway today in Reaches 8 and 9. Every property within Reach 8 and 9 has received sand placement. Crews will complete final touches tomorrow and begin equipment demobilization.
Thank you for your patience and continued attention to safety around construction equipment as this restoration work concludes.
December 17, 2025: Work continues to progress steadily on the Reach 8 and 9 dune restoration project. To date, more than 22,000 cubic yards of sand have been placed. The remaining work is expected to be completed by Tuesday, December 23. Following completion, construction equipment will be shut down for the holidays, with active demobilization beginning after Christmas.
The public can support the project efforts by installing native dune plants on their own beachfront properties where appropriate. Dune vegetation helps stabilize the restored shoreline, reduces erosion, and supports long-term natural dune rebuilding. Homeowners interested in adding dune plantings should contact certified vendors for guidance and installation.
Please continue to use caution near active work zones and follow all posted signage for safety. As always, thank you for your patience and cooperation as we work to strengthen coastal resilience and address erosion along our shoreline.
December 10, 2025: Work is steadily progressing in the Reach 8 and 9 dune restoration project. Approximately 20,000 cubic yards of material have been completed to date. Work has finished at the south end of Reach 8 and is progressing north. The north segment of Reach 8 is expected to be completed in the next couple of days, then crews will focus on completing the portion of the project south of the Atriums.
Please continue to use caution near active work zones and follow posted signage for safety. As always, we appreciate the community’s patience and cooperation as we work to strengthen coastal resilience and address erosion.
December 5, 2025: Work continues to advance on the Reach 8 and 9 dune restoration project.
Crews have placed approximately 16,000 cubic yards of sand to date, passing the halfway point toward the 30,000-cubic-yard goal. Sand placement is currently underway in Reach 8 and will move south to Reach 9 next week.
Please continue to use caution near active work zones and follow posted signage for safety.
As always, we appreciate the community’s patience and cooperation as we work to strengthen coastal resilience and address erosion.
November 26, 2025: Work is progressing on the Reach 8 and 9 dune restoration project. Crews have placed approximately 13,000 cubic yards of sand toward the 30,000-cubic-yard goal for this project. Sand placement will pause for the Thanksgiving holiday and resume on Monday, December 1.
Following completion of construction in December, the Town will restore dune vegetation and the beach access point in Reach 8 by the Atriums. The public can support these efforts by installing native dune plants on their own beachfront properties where appropriate. Dune vegetation helps stabilize the restored shoreline, reduces erosion, and supports long-term natural dune rebuilding. Homeowners interested in adding dune plantings should contact certified vendors for guidance and installation.
Please continue to use caution near active work zones and follow posted signage for safety. As always, we appreciate the community’s patience and cooperation as we work to strengthen coastal resilience and address erosion.
November 21, 2025: Reach 8 and 9 dune restoration work continues to progress as planned. Crews are placing sand steadily, moving north from the Atriums, with 8,800 cubic yards completed so far toward the 30,000-cubic-yard goal. Production is averaging more than 50 loads per day, and operations remain on track.
As construction continues, please use caution near active work zones and follow posted signage for safety. We appreciate the community’s ongoing cooperation as we work to rebuild the dune system, enhance coastal resilience, and protect the shoreline.
November 14, 2025: Crews are off to a strong start on the Reach 8 and 9 dune restoration project. Operations began on Monday, November 10, and in four days, approximately 3,400 cubic yards of sand have been placed to rebuild the dune. Work is moving north in sections of roughly 200 feet at a time, and production is on track to meet or exceed daily goals.
As construction continues northward, nearby condominiums will be notified. Please use caution near active work zones and follow posted signage for safety.
As always, we appreciate the community’s patience and cooperation as we work to strengthen coastal resilience and address erosion.
November 7, 2025: The dune restoration project along Reaches 8 and 9 is moving along smoothly, with sand placement expected to begin early next week. The equipment is already staged, and conveyor installation is in progress. Sand deliveries are expected to start as soon as Monday.
The team continues to coordinate closely with agencies, lifeguards, and nearby condominium managers. Fueling logistics and fencing are being finalized, traffic signage is in place, and weather conditions, including upcoming king tides, will be monitored closely.
As always, we appreciate the community’s patience and cooperation as we work to strengthen coastal resilience and address erosion.
Palm Beach Groin Rehabilitation Program
Project Overview
The Town of Palm Beach’s Groin Rehabilitation Program aims to support individual property owners seeking to remove or rehabilitate existing coastal structures to maintain their function along the shoreline in Reaches 2 through 6. The current inventory includes over 100 groins, dating back to the 1930s and constructed using a variety of materials and designs. Over time, many have deteriorated and now function at varying levels.
The program allows for the removal or replacement of existing groins to support the overall performance of the coastal system, consistent with the Town’s Coastal Management Program, the 2011 Coastal Structures Plan, the Beach Management Agreement, and applicable regulatory authorizations. In order to proceed with approved actions under the Town’s permits, individual property owners should reach out to Public Works at 561-838-5440 and adhere to the process generally described below.
Use of the Town’s Regulatory Approvals
The Town has obtained permits from the Florida Department of Environmental Protection and the U.S. Army Corps of Engineers for groin rehabilitation. Individual property owners may seek approval from the Town Council to utilize these authorizations for conducting permit-approved actions (removal or replacement) at their own cost.
Construction Window
All construction activities must occur between November 1 and April 30 to minimize impacts to nesting sea turtles.
Environmental & Site Considerations
Groin rehabilitation activities are subject to environmental review, regulatory conditions, and monitoring requirements, which include acquisition of the private easement, turbidity monitoring, protection of nearshore hardbottom resources, marine turtle and shorebird monitoring, vessel operation requirements, and other activities as specified by permit conditions. Temporary land and/or water access will be required for project construction.
How to Participate
Property owners interested in removing, rehabilitating, or replacing an existing groin should complete the following steps:
Coordinate with the Town of Palm Beach
Confirm the permitted scope of work (repair, replacement, or removal) and initiate the process with the Town. Contact: Sara Westphal, Coastal Coordinator, 561-838-5440
Retain Professional Engineering Services
A licensed coastal engineer will be required to assess the existing groin condition and prepare design and construction documents consistent with Town requirements and applicable permits. The engineer may also support preparation of regulatory submittals and coordinate with the Town as needed.
Execute a Local Agreement with the Town
A legal agreement is required by the Town that outlines access, coordination, and responsibilities associated with the project in order to work under Town regulatory approvals. The agreement and proposed project will be presented to Town Council at a regular meeting for their approval and signature.
Obtain State and Federal Regulatory Authorizations to Commence Construction
- Prepare an Individual Project Approval (IPA) request to be submitted in coordination with the Town through the Florida Department of Environmental Protection’s (FDEP) Beach Management Agreement (BMA).
- Comply with all conditions of the U.S. Army Corps of Engineers Department of the Army permit and provide Notice of Project Commencement.
Hire a Qualified Marine Contractor
Contractors must be experienced in marine construction and environmental compliance consistent with the work to be performed.
Current Groin Rehabilitation Projects
Town Staff are currently coordinating with private property owners in Reach 5 to remove and replace four groins fronting their beachfront property. The goal of the project is to maintain the current level of function that the existing structures provide while reducing hazards and stabilizing the shoreline. The replacement groins have been designed to generally align with the locations, elevations, and dimensions of the existing groins in their present condition.
The new groin installation work began in December and is expected to be done by sea turtle nesting season beginning May 1. Town staff and consultants are monitoring the construction progress and will be posting regular updates as construction progresses. See below links to our weekly progress reports.
1-22-26 Weekly Progress Report
1-28-26 Weekly Progress Report
2-11-26 Weekly Progress Report
2-18-26 Weekly Progress Report
Beaches and Dunes: Our First Line of Defense
Our town is built on a barrier island and is constantly affected by wind, waves and the movement of sand. Our beach and dune system are the first line of defense in protecting property, infrastructure, quality of life, habitat for nesting sea turtles and other coastal species, and sustaining our island community for the future.
The Town of Palm Beach Coastal Management Plan
The Town has a history of being forward-thinking, proactive and innovative. Our Coastal Management Plan, with leadership from the Town Council and the Town’s Shore Protection Board, is our guide to protecting our coastal resources today and for the future.
In 1986, the Town of Palm Beach adopted the Coastal Management Plan to guide the management, monitoring, and protection of resources and infrastructure along the shoreline. This plan was important in addressing the significant threat posed by coastal erosion, which had reached critical levels by the 1990s, endangering our beaches. Without intervention, the Town of Palm Beach faced the unthinkable prospect of losing its primary attraction and economic engine. The Coastal Management Plan provides a strategic framework for implementing beach renourishment projects and other coastal protection measures to preserve our coastline and the continued prosperity of our community.
The Town of Palm Beach Coastal Management Plan is an essential tool for safeguarding the community’s natural beauty, infrastructure, and overall way of life. Through storm protection, environmental preservation, economic benefits, public engagement, and climate change adaptation, implementation of the Plan ensures that Palm Beach remains a vibrant, resilient, and sustainable coastal community for generations to come.
Reaches
As part of the CMP, segments of the Town's shoreline were delineated according to their shoreline characteristics, upland land use designations, environmental resources mitigation requirements, and shoreline restoration and maintenance requirements. These segments are referred to as "Reaches". The Reaches were established as planning units and used to extrapolate future erosion scenarios when developing the CMP. Additionally, the Florida Department of Environmental Protection (FDEP) has established Range Monuments (R monuments) along Florida's coastline to as coastal survey markers to mark key survey points along Florida's coastline. R monuments are located at approximately 1,000-foot intervals. Palm Beach County R monuments range from R-1 to R-227, and Palm Beach spans from R-76 to R-134. R monuments are often used to define the limits of each Reach.
Reach 1
Lake Worth Inlet to Onondaga Avenue, FDEP R monument R-76 to R-78 (2,410 feet).
Reach 2
Onondaga Avenue to El Mirasol, FDEP R monument R-78 to R-90+400 (13,660 feet).
Reach 3
El Mirasol to Via Bethesda, FDEP R monument R-90+400 to R-95 (5,800 feet).
Reach 4
Via Bethesda to 270 feet south of Banyan Road, FDEP R monument R-95 to R-102+300 (8,065 feet).
Reach 5
270 feet south of Banyan Road to 170 feet north of Widener's Curve, FDEP R monument R-102+300 to R-110+100 (9,065 feet).
Reach 6
170 feet north of Widener's Curve to Sloan's Curve, FDEP R monument R-110+100 to R-116+500 (6,685 feet).
Reach 7
Sloan's Curve to The Ambassador Hotel, FDEP R monument R-116+500 to R-125 (8,725 feet).
Reach 8
The Ambassador Hotel to La Bonne Vie, FDEP R monument R-125 to R-134 (10,690 feet).
Coastal Resilience Implementation Plan 2021, Woods Hole Group
Coastal Vulnerability Assessment 2019, Woods Hole Group
Beach Management Agreement
Comprehensive Coastal Management Plan Update
Live Water Levels in the Town
Get Involved
The Town of Palm Beach encourages residents and visitors to stay informed and engaged in our Coastal Management projects. You can stay informed by:
Attending Town of Palm Beach Shore Protection Board Meetings: Join us for regular meetings to learn more about the projects and share your thoughts. View the Board Meeting Calendar here.
Following us on Social Media: Follow The Town of Palm Beach on Facebook for regular updates.
Stay Updated: For timely updates, bookmark this page in your browser and visit our website regularly.
Contact Us: For more details or to address any questions or concerns regarding the beach construction project, please contact:
Public Works:
pworks@townofpalmbeach.com
Phone:
561-838-5440
Office Address:
951 Okeechobee Rd. Suite A,
West Palm Beach FL 33401