Beginning Tuesday, June 20, 2023, Florida Power & Light (FPL), through its contractor, Wilco Electrical, will be removing the existing FPL utility poles within the Phase 2 South area. The aerial map identifies the streets where they intend to remove the poles the week of June 20th. Project Managers are estimating roughly a day and a half for each street. However, these are estimates depending on any complications with set-up, etc. Since this will be the first week in this tight area, Project Managers would like to see how the first couple of days go, and adjust as necessary as they work north to Clarendon Avenue.